Africa-focused. Operationally grounded.

E2Gx Mobility works exclusively in public transport operations — building the systems, structures, and capability that make services run reliably across Africa.

Learn more
Core Bus, Rail & Metro Operators
Frontier Transport Holdings Limited FTH.JO 611.00 +7.01% Saudi Public Transport Company 4040.SR 11.31 -2.08% ComfortDelGro Corporation Limited C52.SI 1.3000 +0.78% Kelsian Group Limited KLS.AX 4.2900 +1.18% FirstGroup Plc FGP.L 172.50 +1.00% Mobico Group Plc MCG.L 22.58 +1.44% FNM S.p.A. FNM.MI 0.4855 -2.61% MTR Corporation Limited 0066.HK 31.48 -0.38% Transport International Holdings 0062.HK 9.51 +0.21% AMS Public Transport Holdings Limited 0077.HK 0.4300 · 0.00% Taiwan High Speed Rail Corporation 2633.TW 25.75 +1.78% Beijing Shanghai High Speed Railway Co., Ltd. 601816.SS 5.06 -0.78% Tokyo Metro Co Ltd 9023.T 1,387.00 -0.75% East Japan Railway Company 9020.T 3,313.00 -0.96% West Japan Railway Company 9021.T 2,496.00 +0.44% Central Japan Railway Company 9022.T 3,325.00 -1.16% Kyushu Railway Company 9142.T 3,427.00 -0.52%
Japan Listed Rail & Bus Operators
Tobu Railway Co., Ltd. 9001.T 2,753.00 +2.13% Sotetsu Holdings, Inc. 9003.T 2,346.00 -0.45% Tokyu Corporation 9005.T 1,677.50 +2.54% Keikyu Corporation 9006.T 1,466.00 +0.58% Odakyu Electric Railway Co., Ltd. 9007.T 1,652.50 +4.82% Keio Corporation 9008.T 728.20 +1.46% Keisei Electric Railway Co., Ltd. 9009.T 1,044.00 +0.10% Seibu Holdings Inc. 9024.T 2,721.50 -2.73% Nishi Nippon Railroad Co., Ltd. 9031.T 2,732.00 +0.28% Hiroshima Electric Railway Co., Ltd. 9033.T 617.00 · 0.00% Kintetsu Group Holdings Co., Ltd. 9041.T 3,587.00 +2.40% Hankyu Hanshin Holdings, Inc. 9042.T 4,481.00 -0.95% Nankai Electric Railway Co., Ltd. 9044.T 2,644.00 +0.80% Keihan Holdings Co., Ltd. 9045.T 3,192.00 +0.03% Kobe Electric Railway Co., Ltd. 9046.T 2,345.00 +0.99% Nagoya Railroad Co., Ltd. 9048.T 1,828.50 +1.44% Keifuku Electric Railroad Co., Ltd. 9049.T 7,190.00 · 0.00% Sanyo Electric Railway Co., Ltd. 9052.T 1,880.00 +0.75% Kanagawa Chuo Kotsu Co., Ltd. 9081.T 3,345.00 +2.45% Shinki Bus Co., Ltd. 9083.T 1,965.00 -0.25% Hokkaido Chuo Bus Co., Ltd. 9085.S 4,000.00 · 0.00%
Fleet electrification South Africa Client Anonymised Featured

Fleet Electrification — South Africa Pilot

Operational design for a 40-vehicle electric bus transition — charge-aware scheduling, grid resilience planning, and depot electrification specification across two depots serving a national capital.

40

EV Fleet Size

vehicles transitioned

2

Depots Electrified

fully commissioned

6hr

Load Shedding Cover

daily outage tolerance built in

+12%

Schedule Efficiency

vehicle utilisation improvement

Case Study

Challenge, approach, and outcomes.

The Challenge

A national bus operator was transitioning 40 vehicles to electric as part of a climate-linked DFI programme. Vehicle procurement and depot infrastructure contracts had been awarded — but no operational design work had been done. The charging strategy, vehicle schedule, and depot configuration had all been planned on the assumption of stable overnight grid supply, which was inconsistent with local load-shedding patterns of four to six hours per day.

Our Approach

We modelled the energy demand of every route in the network to establish which were viable for the available vehicle range without en-route charging. We then designed a charge-aware vehicle schedule that matched charging windows to the grid's stable periods. The depot electrification specification was revised to include battery storage sufficient to maintain charging capacity through a six-hour outage without service disruption.

Outcomes

The transition was completed on schedule and the full fleet was operational within the planned timeline — without the service gaps that had affected comparable transitions in the region. Vehicle utilisation improved 12% against the diesel baseline because the charge-aware schedule eliminated idle-charging time from the operational day.

Engagement Detail

In detail.

A national bus operator in East Africa was transitioning 40 vehicles to electric as part of a climate-linked DFI programme. The vehicle procurement had been specified and the depot infrastructure contracts had been awarded — but no operational design work had been done. The charging strategy, vehicle schedule, and depot configuration had all been planned on the assumption of stable overnight grid supply, which was inconsistent with local load shedding patterns of four to six hours per day.

E2Gx Mobility was engaged to design the operational layer of the transition. We began by modelling the energy demand of every route in the network, establishing which routes were viable for the available vehicle range without en-route charging. We then designed a charge-aware vehicle schedule that matched charging windows to the grid's stable periods and built in backup capacity for the most common outage scenarios.

The depot electrification specification was revised to include battery storage at each depot sufficient to maintain charging capacity through a six-hour outage without service disruption. The transition was completed on schedule and the full fleet was operational within the planned timeline — without the service gaps that had affected comparable transitions in the region.

Services Delivered

What we did on this engagement.